More foundation work

Before the insulation can be put in place we need to level the entire foundation off with a more granular stone crush. The coarse 0-90mm would not be very suitable for placing the insulation on so we had 20m3 of 4-8mm stone crush delivered and got to work.
Geotextile under the 4-8mm stone crush
To separate the coarser layer with new 4-8mm the whole foundation was covered with geotextile made for foundations. In Sweden, where we build, this is a class N2 geotextile. The geotextile was laid down in sections as we couldn’t drive the excavator over it if we laid it all out at the same time.
Once the geotextile was in place we got to work with the first section. The final foundation level will 250mm over the 4-8mm stone crush. The excavator did a rough leveling and then we manually raked the gravel to get it to within the +/- 10mm of the level we needed to be at. It wasn’t very hard but took a but of time to get it all to the correct height.
It took us about 4 hours to get all the 4-8mm stone crush laid out on top of the geotextile and levelled off to +/-10mm of where we needed it to be. It would have been very painful without a proper rotational laser but thankfully we had one at hand.
Cold water lines
After a well deserved lunch we got another visit from the contractor who’s helping is with all the plumbing and water lines. Since the insulation will not be the standard plastic insulation but instead a foam glass insulation it was decided to put all cold water lines within the 4-8mm gravel. There’s about 100-150mm of finer gravel on top of the geotextile so plenty of room for cold water. The hot water lines will be placed within the insulation just under the floor heating at a later stage.
We also did some final adjustments of the sewer pipes, floor drains and toilet main sewer pipe, which was a little bit off bit was easily fixed by Johannes.
Next steps
We’re on the final stretch of getting the foundation done. In about 2 weeks we’ll put all foam glass insulation in place, followed by the in-floor heating system and finally pouring the slab later that week.