The Wood's Croft

field notes · slow living

· 4 min read

Starting to build the main house

Over the past couple of months the weather has made work progress slower than expected. A colder than usual winter in southern Sweden made it hard to dig (or very expensive) so we just had to accept the situation and wait for better weather.

Continue reading
· 6 min read

Summarizing 2023!

It's been a really long time since we last posted any updates, mostly due to a lot of other work, but also less interesting things to write about. In this post, we'll try to summarize what's happened during 2023.

Continue reading
· 2 min read

More digging

After almost a full week of digging down various types of tubing and pipes we have the sewer system done, the new water well is connected and we ready for the electric company to connect our house to the grid. Very happy to be done with this work.

Continue reading
· 4 min read

Easter weekend of 2022

And so came the great easter weekend of 2022 with high hopes of lots of progress but as many times before, things didn't work out entirely as planned although we did manage to make some good progress.

Continue reading
· 3 min read

Installing doors on the Workshop

Up until this point we've only had some simple boards to cover the small doors and the larger one at the east gable end has only had a sheet of plastic stopping people and animals from getting in. We commissioned the local carpenter to help build the doors and together we installed them.

Continue reading
· 4 min read

A lot of small things

As we learned, it's hard to make progress during winter with less daylight, colder weather and overall less energy to spare. However, we did manage to make some progress over the past few months.

Continue reading
· 4 min read

Fall is here

Fall is here yet again with shorter and colder days. In the past few months we've gotten more cladding in place, got all windows in place and we bought a huge old drawer cabinet for the local hardware store.

Continue reading
· 4 min read

Sheathing, gables and cladding

Long time with no posts but things have been progressing nonetheless. The gables are up, all sheathing are in place, most battens are in place and about 20% of the burnt timber cladding is in place. A lot of learnings in the process but it's nice to finally see some parts of the build actually fully finished.

Continue reading
· 2 min read

New scaffolding and new roof

As we never managed to get north facing roof covered with the first protective layer, it's been covered by 3 large tarps until now. With a new scaffolding purchased we got hold of a great contractor who came in a did a great job in just a few hours covering the whole roof up.

Continue reading
· 3 min read

Workshop sheathing

With the frame up we go to work with the next thing we could do ourselves, the sheathing. While to roof is not done yet the sheathing was something we are ok with doing ourselves.

Continue reading
· 5 min read

The workshop frame goes up

We've been busy the last couple of weeks with the last preparations getting all material, screws, scaffolding, nails, machines etc. in place for the planned easter weekend framing. There was a lot of things that needed to work out right and while not everything went as smooth as we were hoping it's fantastic to finally see frame fully erected.

Continue reading
· 2 min read

Workshop changes

When we designed the workshop roof, its slope was decided based on what we were planning to do on the house to make the roof a distinct connection between the two buildings. However, after a few weeks of thinking and designing we've decided to change the roof slope of the workshop.

Continue reading
· 2 min read

Winter is upon us

Winter is here for real. While it's very beautiful outside it does introduce its fair share of issues when you have a cabin without heating and the temperature drops below freezing.

Continue reading
· 4 min read

Pouring the workshop slab

We're almost at the finish line with the workshop foundation. The only thing left is to pour the concrete slab. An important milestone for the workshop and at the same time a pretty nerve wrecking experience making sure we have not forgotten anything. Once we've poured the slab it's kind of point of no return for a lot of things.

Continue reading
· 3 min read

Radiant floor heating

Now that the insulation is in place we're almost at the point where we can pour the concrete slab and finish the foundation but first the in floor radiant heating needs to be put in place.

Continue reading
· 3 min read

Foundation insulation

With a level gravel foundation in place, the next step is to place all insulation that will decide the outer perimeter of the finished slab as well as the floor height of the finished building. It all started an early, rainy but exciting Friday morning...

Continue reading
· 3 min read

More foundation work

Before the insulation can be put in place we need to level the entire foundation off with a more granular stone crush. The coarse 0-90mm would not be very suitable for placing the insulation on so we had 20m3 of 4-8mm stone crush delivered and got to work.

Continue reading
· 5 min read

Workshop foundation & pipe work

With the foundation marked out we were now ready to take the next step and actually start work on the foundation itself. First up is getting a pipes, sewer system and connections in place.

Continue reading
· 3 min read

Marking out the foundation of the workshop

To prepare for all the plumbing work including septic system, sewage, water supply, etc we've come to the point where we need to mark out the foundation. Most things regarding contractors helping us has been decided and it's time to get busy.

Continue reading
· 2 min read

Clearing a path

We're planning a raised wooden path between the workshop and the house, similar to what you'd find in japanese gardens. Today it was time to clear the path and prepare for some digging.

Continue reading
· 3 min read

Campfire cooking with Muurikka

We've tried a few different ideas for cooking over a campfire but none has really worked that well. They've been pretty crude and not really meant for campfire cooking but when we saw a Muurikka we thought it would be great for us.

Continue reading
· 4 min read

Trying out the new sawmill

There's been a lot of back and forth wether we should buy a sawmill ourselves, rent it or simply have someone else fo it for us. In the end we decided to spend the money once and hopefully get years of nice lumber at a very low cost.

Continue reading