The workshop frame goes up

We’ve been busy the last couple of weeks with the last preparations getting all material, screws, scaffolding, nails, machines etc. in place for the planned easter weekend framing. There was a lot of things that needed to work out right and while not everything went as smooth as we were hoping it’s fantastic to finally see frame fully erected.
Scaffolding
A pre-requisite to even start building the frame and more precisely getting the roof sheathing in place was the scaffolding. We spent a day before easter weekend raising the scaffolding and getting ready for framing. We did plan on buying the scaffolding but due to delivery taking longer than expected we had to rent a frame instead.
Getting the material
The day before easter weekend the plan was to receive all material. That day was quite busy and it was crucial we got everything we needed to be able to erect the full complete frame of the workshop. Most went as planned except the roof sheathing that at first could not be delivered on time but thanks to Peter at our local Derome building supplier we managed to get all materials ready by the end of the day.
The frame goes up
We’ll let the photos tell the story here. A few technical details; all studs used when building the outer walls are 220x45mm. The height of the outer wall, when complete, is exactly 3 meters. The rest is pretty standard.
Day 1
Day 2
Day 3
Aa planned, day 3 started with the crane arriving to help hoist the roof rafters in place which went all smooth. Nice to have professional help.
Day 4
Most of day 3 was good and we progressed pretty much as planned all up until we started putting down the first protective layer. This to a lot longer than expected and threw most of our schedules on its end. Day 4 started on a low note and since the weather was expected to get worse we started sheathing the other side of the roof before finishing the protective layer on the first side.
Almost done
Most days went on according to the plan except the weather getting all weird on day 4 and the slow process of getting the protective layer in place. We ended up just finishing one side of the roof and put a tarp on the other side to protect it from rain for the time being.
Getting the protective layer in place proved harder than we though and we’ve decided to hire a contractor that specializes in roofing to finish the roof for us. Even though things ended on a low note we’re happy with the work we got done. Huge shout-out to Victor and Erik for helping us get this much done in just 4 days 👊🏻 We owe you big time!